Based on construction drawings of MK Constructions, the slab contractor should lay the floor slab to the exact dimensions and ensure the slab is level and has the correct rebates.
Checking the accuracy of the slab and rebate a few days prior to installation so that we avoid any level inaccuracies in the level of the slab and prevent compression contact between the bottom of the panel and the damp course.
Panels will always be installed from the highest point and the lower points packed with appropriate packing material.
Panels must always be installed in an absolutely horizontal plane.
Should any major tolerance problems be evident, the slab contractor should be notified and rectification undertaken.